By the Flori team · Published · Updated

A project plan says how a project will get done: the goal, what is in and out of scope, who does each task, on which working days, in what order, for how much, and who hears what along the way. Below is a blank nine-part template, then one fictional eight-week brand and website project filled in part by part. Download the plan as Markdown or plain text, and the schedule as a blank CSV or the filled example CSV for Excel or Google Sheets.

A project proposal wins the work and a project charter authorizes it and names who may decide. The plan comes after both and turns that decision into owners, dates and order.

The blank project plan template

Copy this into Word, Google Docs or a spreadsheet and fill in the last column.

PartWhat it answersYour plan
1. Goal and success measureWhat changes, measured how, by when?
2. Scope in and outWhat will we do, and what will we not do?
3. DeliverablesWhat will exist at the end?
4. Work breakdownWhich tasks, who owns each, how many working days?
5. ScheduleStart and finish dates, dependencies, milestones
6. BudgetCost lines, contingency, total
7. RisksWhat could go wrong, who watches it, what we do
8. Communication planWho gets which update, how often, from whom
9. Change controlHow a change is asked for and approved

The example, part by part

Marlow Surveying is a fictional 15-person surveying firm. Kestrel Studio, also fictional, is a four-person agency: project lead, designer, writer and developer. The project runs eight weeks, Monday 1 March to Friday 23 April 2027, weekdays only, with no US public holiday.

1. Goal and success measure

New brand and a 10-page website live by Friday 23 April 2027. Measure: quote requests through the site rise from 4 a month (January and February average) to 10 a month by Friday 30 July 2027.

2. Scope in and out

Contract wording for scope belongs in a statement of work.

3. Deliverables

Brief; logo files; brand guidelines; sitemap; 5 page templates; 10 pages of approved copy; redirect map; the live site; a handover note.

4 and 5. Work breakdown and schedule

Days are working days; each task starts the working day after its dependencies finish.

#TaskOwnerDaysStartFinishDepends on
1Kickoff meeting with the clientProject lead1Mon 1 MarMon 1 MarNone
2Interview 5 staff and 3 clientsProject lead3Tue 2 MarThu 4 Mar1
3Audit current site, 38 pagesWriter3Tue 2 MarThu 4 Mar1
4Brief written and approvedProject lead2Fri 5 MarMon 8 Mar2 and 3
5Three logo routesDesigner5Tue 9 MarMon 15 Mar4
6Sitemap and page list, 10 pagesWriter2Tue 9 MarWed 10 Mar4
7Write copy for 10 pagesWriter8Thu 11 MarMon 22 Mar6
8Set up hosting, CMS and stagingDeveloper2Thu 11 MarFri 12 Mar6
9Client chooses a logo routeClient2Tue 16 MarWed 17 Mar5
10Wireframes for 5 page templatesDesigner3Tue 16 MarThu 18 Mar5 and 6
11Refine logo, colours and typeDesigner3Fri 19 MarTue 23 Mar9 and 10
12Client reviews and approves copyClient3Tue 23 MarThu 25 Mar7
13Redirect map for 38 old URLsWriter2Tue 23 MarWed 24 Mar3 and 7
14Visual design of 5 templatesDesigner4Wed 24 MarMon 29 Mar11
15Brand guidelines, 12 pagesDesigner3Tue 30 MarThu 1 Apr14
16Client design review, one roundClient2Tue 30 MarWed 31 Mar14
17Design changes from the reviewDesigner2Fri 2 AprMon 5 Apr15 and 16
18Build 5 templates on stagingDeveloper5Tue 6 AprMon 12 Apr8 and 17
19Load copy and images, 10 pagesDeveloper2Tue 13 AprWed 14 Apr12 and 18
20Test on phones and browsers, fixDeveloper3Thu 15 AprMon 19 Apr19
21Client signs off stagingClient1Tue 20 AprTue 20 Apr20
22Launch site and redirectsDeveloper1Wed 21 AprWed 21 Apr13 and 21
23One-hour editor training and handoverProject lead1Thu 22 AprThu 22 Apr22

"Client" means the office manager, who sends one combined response. Task 17 waits for task 15 only because one designer does both: a person can be a dependency. Friday 23 April is slack.

MilestoneDateSet by task
Brief approvedMonday 8 March4
Logo route chosenWednesday 17 March9
Copy approvedThursday 25 March12
Design approvedWednesday 31 March16
Staging signed offTuesday 20 April21
LaunchWednesday 21 April22
HandoverThursday 22 April23

6. Budget

Fees are working days times day rate; the project lead's 12 days are 7 task days plus 5 for calls and reviews. Tracking costs line by line is covered in the project budget template.

LineCalculationAmount
Project lead12 days at $900$10,800
Designer20 days at $750$15,000
Writer15 days at $650$9,750
Developer13 days at $800$10,400
Font licence, stock photos, a year of hosting$400 + $350 + $300$1,050
Subtotal$47,000
Contingency, 10%, released by the managing director$4,700
Total$51,700

7. Risks

RiskLikelihoodOwnerResponse
Client reviews overrunMediumOffice managerAll four review windows booked at kickoff
No logo route chosen in task 9MediumProject leadOne extra 3-day round ($2,250) from contingency
Old site has more than 38 URLsLowWriterFull crawl in task 3; extras priced before work starts
Designer away for a weekLowProject leadDeveloper builds from wireframes; use contingency

8. Communication plan

WhoWhat they getHow oftenFrom whomHow
Managing director (sponsor)Done, next, decisions needed, budget usedFridaysProject leadEmail, five lines
Office managerThis week's tasks and what is waiting on the firmMondays, 30 minutesProject leadVideo call
Partners reviewing workReview dates and what to check2 working days before each reviewOffice managerEmail
All Marlow staffWhat is changing and whenKickoff and launchManaging directorStaff meeting

Who approves and who is informed belongs in a RACI chart; task 1 can follow a kickoff meeting agenda.

9. Change control

Any change to scope, to a milestone date, or over $500 goes to the project lead in writing. The lead prices it in days and dollars within 2 working days; the managing director approves or declines. Approved changes enter the plan with their approval date.

A simple one-page project plan for projects under a month

A short project needs goal, scope, dated steps and one risk. Fictional example: a 9-person cleaning company updates its prices, Monday 10 May to Friday 28 May 2027.

LineExample
GoalNew prices published by Friday 28 May, customers told 30 days before they apply
In and outIn: price sheet, pricing page, customer email. Out: new services, website redesign
StepsCollect last year's prices, office manager, Mon 10 to Tue 11 May; draft prices, owner, Wed 12 to Fri 14 May; page copy, writer, Mon 17 to Wed 19 May; owner approves, Thu 20 May; page updated, web freelancer, Fri 21 to Mon 24 May; customer email, office manager, Tue 25 May
Budget$1,200 for the two freelancers
Biggest riskOwner approval slips; Wednesday 26 to Friday 28 May are slack
UpdatesOwner and office manager, 10 minutes each Monday

How to build the schedule in Excel or Google Sheets

  1. Set up the columns: ID, Phase, Task, Owner, Days, Depends on, Start, Finish, Baseline start, Baseline finish, Slip (A to K). The CSVs above use this order. Mistake: no Days column, so dates are typed by hand and drift.
  2. Type only the first start date. Finish in H2 is =WORKDAY(G2,E2-1). WORKDAY returns the date a given number of working days after the start, skipping Saturdays and Sundays (Google Sheets, Excel), so a 1-day task finishes on its start day. Mistake: =G2+E2, which counts weekends.
  3. Chain the starts. A task that depends on row 5 starts =WORKDAY(H5,1); on rows 3 and 5, =WORKDAY(MAX(H3,H5),1). Mistake: typing start dates, so one late task moves nothing after it.
  4. Add holidays. List them on a tab named Holidays and pass that range as WORKDAY's third argument: =WORKDAY(G2,E2-1,Holidays!$A$2:$A$12). If Excel shows a number such as 46447, format the cell as a date.
  5. Draw a text Gantt. Put each week's Monday across row 1 from column L (=L1+7 in M1), select the grid below it, and add a formula rule: in Google Sheets, Format, Conditional formatting, "Custom formula is" (Google's steps); in Excel, Home, Conditional Formatting, New Rule, "Use a formula to determine which cells to format" (Microsoft's steps). The rule =AND(L$1<=$H2,L$1+4>=$G2) colours each week a task touches. Mistake: bars drawn by hand.

How to baseline the plan and track against it

When the sponsor approves the plan, copy Start and Finish and paste values only into the two Baseline columns, then never edit them. Each week, =H2-J2 in a Slip column (K) shows calendar days late against the baseline, and any milestone that slips goes in the sponsor's Friday email. Re-baseline only for an approved change, keeping the old baseline on a second tab. Weekly status across several live projects is the job of a project tracker template.

Five ways project plans go wrong

  1. Calendar days instead of working days. An 8-day task counted in calendar days ends days too early on paper.
  2. The client's work is missing. Reviews are tasks with owners and days, like tasks 9, 12, 16 and 21.
  3. People are not dependencies. One designer cannot do tasks 15 and 17 at once.
  4. No baseline. Dates get quietly re-typed and nobody knows how late the project is.
  5. Changes without a rule. "Can we add a careers page?" becomes two unpaid days. Part 9 stops it.

Where Flori fits

Flori is a CRM with project management for teams of 1 to 20. The work breakdown becomes tasks with owners, due dates, subtasks and dependencies, a task waiting on the client stays visibly blocked, and a time log on tasks records the time really spent. On every plan, a project's tasks can also be shown as a Gantt chart: bars by week, month or quarter, with dependency lines, milestones and the critical path. Dragging a bar shows which dependent tasks would move and by how much, and nothing changes until you confirm. The free plan covers 3 active projects; for more at no cost, a spreadsheet does the job. Work that flows without fixed dates suits a board like these kanban board examples.

FAQ

What should a project plan include? A measurable goal, scope in and out, deliverables, tasks with owners and estimates, a schedule with dependencies and milestones, a budget, risks, a communication plan and a change rule. A small team fits all nine on two pages.

Is a project plan the same as a project management plan? In everyday use, yes. In formal methods it is a larger document that also says how scope, cost, quality and risk will be managed; small teams rarely need more than these nine parts.

Do agile projects need a project plan? Yes, a lighter one. Keep the goal, scope, budget, milestones and communication plan, and plan tasks a sprint or a week at a time.

Can I use this template in Word or PowerPoint? Yes. Paste the plain-text file into Word, or a table from this page into a slide.